Dubai Metro Blue Line 29% complete, opening set for 2029

The RTA says the 30 km Blue Line is 29% built, with 14 stations planned and a scheduled opening on 9 September 2029.

By Dalil DXB newsroom · · 2 min read

Dubai Metro Blue Line 29% complete, opening set for 2029

Dubai's Roads and Transport Authority (RTA) says the Metro Blue Line is now 29% complete, after Sheikh Hamdan bin Mohammed, Crown Prince of Dubai, toured the Dubai Festival City worksite on 22 November 2026, according to the Dubai Media Office.

Where construction stands

The Dubai Media Office reported that more than 14,000 workers have logged over 33 million working hours on the project. By component, underground stations are 32% complete, tunnel excavation 55%, elevated stations 16% and bridge works 17%. Bridge piers have reached 62%.

The line will cover 30 km, of which 15.5 km is underground and 14.5 km elevated. It will have 14 stations, three of them interchanges: two linking to the Red and Green Lines and one joining the line's two branches. It will also cross Dubai Creek on a 1.3 km bridge built from precast concrete segments, a method the RTA says limits the need for floating cranes and keeps marine traffic moving.

Which areas it will serve

The route is planned to connect Mirdif, Al Warqa'a, International City, Dubai Silicon Oasis, Dubai Academic City, Dubai Festival City and Dubai Creek Harbour. The authority links the project to the Dubai 2040 Urban Master Plan, which promotes development around public transport stations.

New trains and payments

The trains shown during the visit will offer Gold Class, Silver Class and a dedicated carriage for women and children. According to the RTA, the fleet will carry cameras that detect obstacles on the track and count passengers to monitor crowding.

Separately, officials said the next generation of nol–Jaywan cards, developed with Al Etihad Payments, is launching this month.

Opening date

The National reported that the line is scheduled to open on 9 September 2029 and put the project cost at AED 20.5 billion, a figure that did not appear in the Dubai Media Office release.

For residents of the eastern and southern districts, the scheduled opening is nearly three years away, so Metro access remains a future factor in housing and commuting decisions rather than a current one.